2-19-09, 38 degrees, rain CPM Construction continuing on pile driving work and removal of existing sidewalk to expose top of old wall cribbing. Photos of Work:
2-18-09 8:00 AM 20 degrees, sunny CPM crewing are priving piles on site. Excavator on site has removed approximately 200 ft. of sidewalk behind the new seawall to the top of old wall cribbing. This is prep work for driving piles to final elevation level. Photos of today's work:
9:00 am 2-16-09 28 degrees, cloudy CPM on site pile driving Beach walkers viewing work. Workers not too concerned about working on Presidents Day. Photos of today's work:
2-12-09, 11:30 am 50 degrees cloudy. CPM on site and installing sheet piling. Welder installing weep hole pipe in stock pilings. High tide bringing water to base of wall. Photos of today's work: