Wednesday, February 25, 2009

Seawall Reconstrction 2-25-09

2-25-09 10:00 am 25 degrees, partly cloudy.
Workers on site setting steel sheet piles to final grade. Photos of work:
 
 
 
Posted by Picasa

Monday, February 23, 2009

Seawall Reconstruction 2-23-09

1:30 pm, 34 degrees sunny, windy. Workers installing the last few pieces of seawall sheet piling. Top of existing wall being removed by excavator. 
 
 
Posted by Picasa

Thursday, February 19, 2009

Seawall Reconstruction 2-19-09

2-19-09, 38 degrees, rain
CPM Construction continuing on pile driving work and removal of existing sidewalk to expose top of old wall cribbing. Photos of Work:



Posted by Picasa

Wednesday, February 18, 2009

Seawall Reconstruction 2-18-09

2-18-09 8:00 AM
20 degrees, sunny
CPM crewing are priving piles on site. Excavator on site has removed approximately 200 ft. of sidewalk behind the new seawall to the top of old wall cribbing. This is prep work for driving piles to final elevation level. Photos of today's work:




Monday, February 16, 2009

Seawall Construction 2-16-09

9:00 am 2-16-09
28 degrees, cloudy
CPM on site pile driving
Beach walkers viewing work.
Workers not too concerned about working on Presidents Day.
Photos of today's work:


Friday, February 13, 2009

Seawall Work 2-13-09

12-13-09 12:30 pm 35 degrees, partly sunny
CPM on site driving piles.
Photos of Work:




Thursday, February 12, 2009

Seawall Work 2-12-09

2-12-09, 11:30 am 50 degrees cloudy.
CPM on site and installing sheet piling. Welder installing weep hole pipe in stock pilings.
High tide bringing water to base of wall. Photos of today's work:






Wednesday, February 11, 2009

Seawall Work 2-11-09

Vibratory Hammer Driving Sheet Pile

Seawall Work 2-11-09

Weather is 50 degrees and sunny
CPM Contractors on site driving piles
4 sheets driven yesterday afternoon.
4th sheet of today being driven at 8:15 am
Photos of today's work:

Tuesday, February 10, 2009

Gooches Beach Seawall Work 2-10-09


Time 1:00 pm
2-10-09
CPM workers on site prepping for pile driving
Steel sheets on site.





Photos of CPM workers on site today