4-23-09 9:30 am 45 degrees, windy, partly cloudy
CPM on site placing concrete sidewalk. 4 sections scheduled for placement today.
Thursday, April 23, 2009
Friday, April 17, 2009
Seawall Reconstruction 4-17-09
Thursday, April 16, 2009
Seawall Reconstruction 4-16-09
Wednesday, April 15, 2009
Seawall Reconstruction 4-15-09
Friday, April 10, 2009
Wednesday, April 8, 2009
Seawall Reconstruction 4-8-09
Monday, April 6, 2009
Seawall Construction 4-6-09
4-6-09, 10:00 am 50 degrees, sunny, CPM on site, Scott Gibson of DeLuca Hoffman on site.
Workmen installing formwork for concrete sidewalk. Formwork conforming to outline of sheetpile driven against old seawall. There will be horizontal waves in the edge of sidewalk face to reflect this. Rain has aided compaction of subgrade at new sidewalk. CPM plans to place concrete sidewalk (first formed phase) on Thursday 4/9.
Workmen installing formwork for concrete sidewalk. Formwork conforming to outline of sheetpile driven against old seawall. There will be horizontal waves in the edge of sidewalk face to reflect this. Rain has aided compaction of subgrade at new sidewalk. CPM plans to place concrete sidewalk (first formed phase) on Thursday 4/9.